Externally the works are approaching completion. All of the garden wall has been raised to the top level and the copings laid. However, the slow supply of the remaining stone is hampering completion of the paved areas.
Window cleaning is in progress and will continue this week. The installation of the final Swift box in the west wing has been completed.
Internally on the ground floor, the paving has been completed and the pebble boarder filled.
The main glass front door on the east wing has been installed and Access Control features are being installed this week.
Decorations of the staircases and the corridors are progressing.
In the bedrooms and kitchenettes, the initial Builders Clean and the final coating of the timber floors has been carried out.
Commissioning of the BMS controls is being completed together with heating, hot water, and ventilation supplies.
Electrical testing of the emergency lighting, Fire alarms, AOV’s and disabled refuge systems have been completed and certificates have been issued.
Last week demonstration days for the M&E systems were carried out for college staff.