The basement works are still progressing well with more vertical works in the south-east corner and decking for the ground floor slab construction in the west and south wings.
All lift shaft walls were poured last week as were the remaining column and walls in the south wing
Both internally and externally, the JW Cottage 7 temporary support and restraint works have all been carried out. The removal of the rubble wall has also been carried out so that the ground floor slab can progress
This week will see more pouring of walls along the east wing and preparation for further pouring on the ground floor slab.
Daily deliveries of concrete as more elements become available to pour are expected, together with regular skip exchanges.